Marine Works
Between 2025 and 2035, the construction of the Sizewell C Nuclear Power Station will comprise various marine elements. A permanent Beach Landing Facility, will be constructed to facilitate the delivery of various materials and components by water, rather than by rail or road.
A temporary jetty called a Marine Bulk Import Facility is also proposed, which will allow large north sea barges to berth up close to the site to off-load aggregate. There will also be a variety of intake and outfall tunnels built in the harbour below the seabed to provide water to the nuclear plant.
The proposed marine components are shown in the image below:

Marine Works Programme
There will be extensive activity within the harbour from September 2025 onwards. The programme below shows the indicative start and end points of marine works up until the end of 2027.
| Sizewell C Marine Works Programme | ||
| Type | Activity |
2025
Q3
Q4
2026
Q1
Q2
Q3
Q4
2027
Q1
Q2
Q3
Q4
|
|---|---|---|
| Temporary Sea Defence | Piling |
July
August
September
October
November
December
January
February
March
April
May
June
July
August
September
October
November
December
January
February
March
April
May
June
July
August
September
October
November
December
|
| Combined Drainage Outfall | Dredge, pipe install, head structure |
July
August
September
October
November
December
January
February
March
April
May
June
July
August
September
October
November
December
January
February
March
April
May
June
July
August
September
October
November
December
|
| Desalination Pipeline | Dredge, pipe install, head structure |
July
August
September
October
November
December
January
February
March
April
May
June
July
August
September
October
November
December
January
February
March
April
May
June
July
August
September
October
November
December
|
| Marine Bulk Import Facility | Dredge, piling, platform, fenders |
July
August
September
October
November
December
January
February
March
April
May
June
July
August
September
October
November
December
January
February
March
April
May
June
July
August
September
October
November
December
|
| Beach Landing Facility | Dredge, piling, platform, fenders |
July
August
September
October
November
December
January
February
March
April
May
June
July
August
September
October
|